Client: TurbineX
End Client: Leading Natural Gas Producer
Industry: Oil & Gas
Location: Wyoming, USA
Project Type: Design & Delivery of Custom Low-Voltage MCCs
Scope: Emergency Design | Fabrication | Testing & Delivery
TurbineX engaged Current Group on behalf of a major natural gas producer constructing a new gas plant in Western Canada. The client had initially ordered four low-voltage motor control centers (MCCs) from Schneider Electric, enduring an estimated ten-month lead time. Then, just two weeks before delivery, they were notified of an additional four-to-six-month delay.
This last-minute setback jeopardized the entire construction schedule. With commissioning deadlines approaching and no time for further delay, TurbineX needed a trusted partner capable of designing and delivering a fully customized MCC package on an accelerated timeline, without compromising quality or compliance.
Recognizing the urgency, Current Group mobilized immediately with a detailed proposal and a clear, execution-ready plan.
From Critical Delay to On-Time Delivery
Current Group committed to engineering, fabricating, and delivering 75 feet of custom low-voltage MCCs within just 10 weeks — a fraction of the typical industry turnaround.
The project scope included:
- 2 × 2000A, 600V MCCs
- 2 × 1600A, 600V MCCs
To achieve this, our team launched parallel work streams for engineering, procurement, and fabrication to ensure that every step advanced without delay.
Design-Build Approach
Our integrated design-build model gave us full control of the process, from initial engineering through testing and delivery, allowing us to meet the client’s urgent timeline with precision.
Execution highlights:
- Engineering & Design: Completed comprehensive custom electrical and mechanical designs to match plant specifications and utility standards.
- Strategic Procurement: Fast-tracked component sourcing from multiple suppliers, using air freight for critical parts to eliminate shipping delays.
- Fabrication & Assembly: Constructed all MCC sections in-house with a focus on quality, space optimization, and long-term reliability.
- Testing & QA: Conducted complete factory acceptance testing (FAT) and ensured compliance with all applicable standards.
Delivery: Successfully delivered all MCCs to site, meeting the client’s required timeframe and keeping construction on schedule.

Key Takeaways
The outcome demonstrated how disciplined coordination, in-house expertise, and precise execution can overcome even the most challenging timelines. Through seamless collaboration between engineering, procurement, and fabrication teams, Current Group transformed a critical supply chain setback into a success story, delivering a fully custom MCC package that met every performance, safety, and scheduling requirement under intense time constraints.
| Project Focus | Outcome |
|---|---|
| Timeline | 4 custom MCCs (75 ft total) designed, built, and delivered in just 10 weeks |
| Project Continuity | Avoided a 4–6 month delay, keeping the gas plant construction on schedule |
| Quality | Met all electrical code and client specifications with precision fabrication and full QA testing |
| Client Satisfaction | Exceeded expectations in delivery speed, communication, and professionalism |
Why It Worked
Delivering four custom MCCs in just ten weeks required more than technical capability, it demanded complete operational alignment. Current Group’s success on this project came from a combination of in-house control, disciplined project management, and a client-first mindset. By managing every phase internally and maintaining constant communication with TurbineX, our team turned an impossible deadline into a coordinated achievement built on precision, accountability, and expertise.
- Full Process Control: With design, fabrication, and testing handled entirely in-house, there were no coordination bottlenecks.
- Focused Project Management: Engineering, procurement, and production teams worked in lockstep to meet each milestone.
- Client-Aligned Priorities: Every decision centered on TurbineX and their client’s top goals — speed, quality, and dependability.
Powering Reliable Solutions for the Energy Industry
Current Group’s ability to mobilize quickly, manage every detail internally, and deliver complex electrical systems under tight deadlines continues to set us apart in the oil and gas sector. Our design-build approach ensures clients get precision-engineered equipment, proven reliability, and results delivered exactly when needed.
Keep your next project on schedule with confidence. Contact Current Group to learn how our custom MCC design and fabrication solutions can meet your most demanding timelines.





